The west box appears all but done. They got the facade up on the ramp side to close in the structure. Looks like there will be some kind of storage area underneath those stands.
Poured the final slab on the east side loge box today, just need to put in the stairs now.
Touchdown club went much slower than I anticipated today. The rain may have hampered what they could get done there. 3 more pours for that though.
NE complex, finally saw some progress on the support beam forms. They built the rebar cage on the northern most beam. Would expect that to be formed up and poured in the next day or two as well.
They are making good progress. Looks like it is going to be tight though to make that opening night game.
Poured the final slab on the east side loge box today, just need to put in the stairs now.
Touchdown club went much slower than I anticipated today. The rain may have hampered what they could get done there. 3 more pours for that though.
NE complex, finally saw some progress on the support beam forms. They built the rebar cage on the northern most beam. Would expect that to be formed up and poured in the next day or two as well.
They are making good progress. Looks like it is going to be tight though to make that opening night game.